Projects Details

SAVAR

Gas Distribution Line Replacement

From 29 June 2025 to 20 July 2025, leakage repair and replacement works were carried out on the 3" gas distribution line at Barodeshi Village, Aminbazar.

The project involved the replacement of a 3" × 360-foot gas distribution pipeline, positioned at a depth of 27 feet below ground level. All works were executed under the supervision of Titas Gas Transmission and Distribution PLC. The replacement and restoration works were successfully completed within the scheduled period.

Project Location

Barodeshi Village, Aminbazar, Savar.

GENERAL PROGRESS 100%

Project Type

Gas Distribution Line Replacement

PHASE 1 (Leakage Repair and Excavation) 100%

Project Cost

Confidential

PHASE 2 (Pipeline Replacement and Welding) 100%

Client

Titas Gas Transmission and Distribution PLC

PHASE 3 (Backfilling and Safety Inspection) 100%